Weekdays one day off in schedules

Discussions about Z-Way software and Z-Wave technology in general
Post Reply
gpostuma
Posts: 2
Joined: 16 May 2012 14:05

Weekdays one day off in schedules

Post by gpostuma »

When writing a schedule that contains a weekday things don't work as I expect.
It seems that the weekday is one day off, for example if today is Friday the schedule does not work when I put in as weekday Friday, but it does work if I enter Saturday.

Suppose today is Friday:
A schedule that only uses Friday fails.
Also creating a schedule that uses all days except the next day (Saturday) fails.
As mentioned above, a schedule that uses only Saturday works.

This behaviour is consistent for every weekday.

A detail that is also present: when entering a weekday, the initial value is always Tuesday, while Sunday or Monday would be more logical.

Is this a known issue, or can there be something wrong in the server/software?
User avatar
PoltoS
Posts: 7579
Joined: 26 Jan 2011 19:36

Thank you for your bug report.

Post by PoltoS »

There was a problem in the UI. On the server side everything was OK. Not the problem is fixed (will be updated in 30 minutes) and you can check it.
gpostuma
Posts: 2
Joined: 16 May 2012 14:05

Solved!

Post by gpostuma »

Thanks for your quick update. Schedules work as expected again.